A backup is only worth something once it can be restored. According to the BSI module CON.3, you must test regularly whether this works flawlessly and within a reasonable time; for essential and important entities, such tests have been mandatory since October 2026 under the NISG 2026 and the Annex to IR (EU) 2024/2690, including documentation of the results. This template provides a log for that purpose: test type and objective, preconditions, procedure with timestamps, achieved recovery time and data state against RTO and RPO, integrity check, findings with deadlines, sign-off and a test plan for the year. It is based on BSI Standard 200-4, the modules CON.3 and DER.4, and NIST SP 800-34.
Contents
Testing restores: recommendation and obligation
Backing up data regularly does not automatically ensure that it can be restored without problems (BSI IT-Grundschutz, module CON.3, threat 2.2). The module therefore requires, as a basic requirement, regular tests of whether backed-up data can be restored flawlessly and within a reasonable time (CON.3.A15). For Austrian companies, IT-Grundschutz is a recognized recommendation, not an obligation. The numbers refer to the Kompendium Edition 2023. According to the BSI, its successor Grundschutz++ can be certified from January 1, 2027, and IT-Grundschutz until November 30, 2031; its user catalog lists the restore test as NOT.4.16.1 (SHOULD, based on representative samples). Binding requirements arise from the NISG 2026 and, for personal data, from the GDPR:
| Basis | Applies to | What is required |
|---|---|---|
| § 32 para. 4 lit. c NISG 2026, in force since Oct 1, 2026 | essential and important entities, unless equivalent sector-specific EU requirements apply (§ 27 NISG 2026; financial sector: DORA, § 4 para. 2) | Business continuity, such as backup management and disaster recovery, as a risk management measure. |
| Annex points 4.2.2, 4.2.3 and 4.2.6 Implementing Regulation (EU) 2024/2690, directly or via § 2 NISV 2026 (Austrian NIS Regulation 2026) | essential and important entities; directly for the providers named in Art. 1 of the Implementing Regulation (including cloud, data centers, managed services) | Backup plans with recovery times; regular integrity checks; regular testing of the restoration of backup copies and redundancies to ensure that they are reliable and cover all necessary copies, procedures and knowledge; document results and take corrective action where necessary. |
| Art. 32(1)(c) and (d) GDPR | Controllers and processors | The ability to restore the availability of personal data in a timely manner after an incident; a process for regularly testing the effectiveness of the measures. |
| BSI CON.3.A15 (basic), DER.4.A1 (standard), DER.4.A10 (elevated protection needs) | Recommendation for everyone | Regular restore tests (A15); use tests and exercises to check whether the measures in the emergency manual work as intended (A1); with elevated protection needs, test emergency plans regularly and when there is cause, and maintain an exercise plan (A10). |
Define the test plan
In the test plan (Section 04), enter for at least twelve months which system is tested when and with which test type; management approves it (BSI Standard 200-4, ch. 13.3).
Fill out one copy per test
Part A before the test, Part B during it, Parts C and D afterward. Track findings until a successful retest.
The structure and fields are a TOMORIS recommendation. BSI Standard 200-4 provides for an exercise concept, an exercise log and an exercise report for each exercise and allows them to be combined in one document (ch. 13.2). Replace placeholders such as [System], [Name, role] and [MM/DD/YYYY] and fill in the “__________” fields. The GDPR does not mention the test explicitly; in TOMORIS’s view, it is an obvious way to verify the ability under lit. c.
Four test types
| Test type | What is tested | Basis |
|---|---|---|
| File | Restore files, folders or data sets from a backup and open them: readable, complete, desired state? | Readability and restoration tests (BSI Standard 200-4, Table 34, ch. 13.9.1); CON.3.A15 |
| System | Restore a server, virtual machine or database server including its configuration to replacement or test hardware and put it into operation; measures the recovery time. | Recovery test (Table 34); recovery to an alternate platform (NIST SP 800-34, 3.5.1); configuration data (Implementing Regulation Annex point 4.2.2(b)) |
| Full recovery | Bring all time-critical systems back up in the defined order, including dependencies, until the business unit can work. | Plan and practice a black start, i.e. recovery of all servers and systems (BSI ransomware catalog of measures, ch. 2); full restoration for high-impact systems (NIST, 3.5.4); sequence (CON.3.A4) |
| Offline or immutable copy | Is the copy truly separated or locked against deletion and overwriting? Then restore from exactly this copy. | Check the separation (ransomware catalog of measures, ch. 2); protection against overwriting (CON.3.A14); not in the same network (Implementing Regulation point 4.2.2(c)) |
It is often sufficient to test the time-critical parts in incremental stages (BSI Standard 200-4, ch. 13.9); deputies should practice too (ch. 13.2). Check for the offline copy: a (domain) administrator tries to access the separated copies; this should fail (ransomware catalog of measures, ch. 2). TOMORIS recommendation: test deletion locks only on a test backup created specifically for this purpose. Under point 4.2.6 of the Implementing Regulation Annex, NIS2 entities also test redundancies, for example failover between redundantly designed systems (BSI Standard 200-4, Table 34); you can use Parts B to D accordingly for this.
Terms: target values and measured values
- MTPD (MTA), maximum tolerable period of disruption
- The maximum time a business process may be down before intolerable impacts occur; determined in the business impact analysis (BSI). NIST calls the corresponding value MTD (Maximum Tolerable Downtime).
- RTO (WAZ), required recovery time
- BSI: from the declaration of the emergency to the required commissioning of the emergency solution, such as resetting an IT system to the last backed-up state; shorter than the MTPD, because the response time is subtracted from it. NIST: the maximum time a system resource can be unavailable without unacceptable consequences for processes and the MTD.
- RPO, maximum acceptable data loss
- The maximum age of available data that still allows meaningful work in emergency operations; the backup cycle follows from it (BSI). NIST: the point in time before the outage to which data can be recovered with the most recent backup.
- RTA, actual recovery time
- The actually achievable period from the declaration of the emergency to the emergency solution being put into production. It is compared with the RTO and can be determined and demonstrated in exercises and tests; without a realistic estimate, it is considered unknown (BSI).
- RPA, actual data loss
- The actual value against which the RPO is compared; in addition, the RPO must be aligned with the backup cycle (BSI, ch. 8.2).
- BAO response time
- BAO stands for Besondere Aufbauorganisation (special organizational structure), meaning the emergency organization with the crisis team. The BAO response time runs from the occurrence of the damaging event through detection and alerting to the declaration of the emergency; MTPD minus response time, minus a buffer where applicable, gives the RTO (BSI, ch. 2, 5.5.1 and 7.2.1). TOMORIS note: a restore test does not measure it. The actual detection time can only be estimated or derived from real events (ch. 13.10.2).
Test plan for the year
Annual exercise planning should cover at least twelve months and record for each exercise the period, type, objective and scope, responsible persons, participants, resources and the expected impact on normal operations (BSI Standard 200-4, ch. 13.3). For NIS2 entities, the tests must ensure that backup copies and redundancies are reliable in an emergency and cover all copies, procedures and knowledge required for effective recovery; the Implementing Regulation Annex does not specify a frequency, only “regularly” (point 4.2.6). The sample policy in NIST SP 800-34 provides for annual tests of recovery capability (Section 3.1). The BSI frequencies below are an example, not a requirement.
| Test type | Frequency | Origin |
|---|---|---|
| System | at least annually for an RTO under 24 h, at least every 3 years for an RTO under 5 days | BSI example for functional tests (Table 37); for NIS2, see the note below |
| File | one sample per backup job monthly, weekly for highly critical data, and also immediately after significant changes; the sample alternates between the copies | TOMORIS recommendation, based on the ENISA example for point 4.2.6 |
| Offline or immutable copy | check separation or lock quarterly; regularly draw file samples from this copy as well | TOMORIS recommendation |
| Full recovery | at least annually, as a tabletop review and as a technical test in incremental stages up to full restoration to a known state | TOMORIS recommendation, based on ch. 13.9 and ENISA on point 4.1.4 |
| Event-driven | after significant security incidents and significant changes to operations or risks (Implementing Regulation), after system or organizational changes (NIST); TOMORIS recommendation: also after a change of backup software, storage target or service provider | Implementing Regulation point 4.1.4 for the contingency plan; NIST SP 800-34, 3.5; BSI Standard 200-4, ch. 13.2; DER.4.A10 (elevated protection needs) |
For NIS2 entities: the ENISA implementation guidance on the Implementing Regulation (Technical Implementation Guidance, June 2025, not legally binding) gives as an example for point 4.2.6 weekly checks for highly critical data, monthly checks for medium and low criticality, and a check immediately after significant changes. For point 4.1.4, it recommends testing contingency and recovery plans at least annually, including as a tabletop review, and including full restoration to a known state in the recovery plan tests.
| Period | Test type, system, objective | Responsible, participants | Resources, impact on operations | Completed on |
|---|---|---|---|---|
| __________ | __________ | __________ | __________ | __________ |
| __________ | __________ | __________ | __________ | __________ |
| __________ | __________ | __________ | __________ | __________ |
| __________ | __________ | __________ | __________ | __________ |
Part A: Test concept and preconditions
| Item | Entry |
|---|---|
| Test no.; test type: file, system, full recovery, offline or immutable copy | __________ |
| System, service or data set tested; target values RTO, RPO and MTPD, see Part C | [System] |
| Objective and measurable success criteria, e.g. RTA no more than RTO, business unit confirms functionality | __________ __________ |
| Date, start, end; announced yes or no; environment: isolated test environment, replacement hardware or production | [MM/DD/YYYY], __:__ to __:__; __________ |
| Exercise lead; performers, logging, observation with role and name; service providers | [Name, role] |
| Backup used: job, timestamp of the data state, copy or medium, location | __________ __________ |
- Risk assessment, risk-reducing measures and abort criteria defined, the way back to the initial state prepared; management approval if the test may affect operations (BSI Standard 200-4, ch. 13.9.1).
- Test environment realistic but isolated from production; setup and teardown planned (ch. 13.9.1).
- The restore instructions are also available outside the backup system, for example on paper, and are used in the test (CON.3.A6, threat 2.4).
- Keys for encrypted backups are available from separate storage (CON.3.A13, elevated protection needs); replacement or test hardware is ready (NIST SP 800-34, 3.5.1); with online storage, the backup system and network connection achieve the permissible recovery time (CON.3.A9).
- Procedure coordinated with service providers that operate backup or recovery, tested jointly where appropriate (DER.4.A16, elevated protection needs); for NIS2 entities, the ENISA implementation guidance on point 4.2.6 also recommends involving suppliers in tests.
- Deputies practice too (BSI Standard 200-4, ch. 13.2, there for the roles of the emergency organization). TOMORIS recommendation: where possible, the deputy performs the restore following the documented instructions.
Part B: Procedure with timestamps
The log should be concise and understandable to expert third parties (BSI Standard 200-4, ch. 13.2). TOMORIS recommendation: take all timestamps from the same clock and define T0 in advance.
| Time | Step | Who | Result, remark |
|---|---|---|---|
| __:__ | T0: test start, represents the declaration of the emergency and the assumed outage | __________ | __________ |
| __:__ | Backup selected and provided: job, timestamp of the data state, copy | __________ | __________ |
| __:__ | Backup checked for malware and damage before restoring | __________ | __________ |
| __:__ | Restore started | __________ | __________ |
| __:__ | Restore completed; data volume, net duration | __________ | __________ |
| __:__ | Integrity and functionality checked (Part C) | __________ | __________ |
| __:__ | T1: system handed over to the business unit for use | __________ | __________ |
| __:__ | Deviation, interruption or intervention | __________ | __________ |
| __:__ | Teardown completed, initial state restored | __________ | __________ |
In case of unintended impact on operations, abort according to the defined criteria and restore the initial state as quickly as possible (ch. 13.9.1); the exercise lead checks the abort criteria continuously (Table 36). Everything created specifically for the test is reversed afterward (ch. 13.9.1).
Part C: Measurement and integrity check
How to calculate (TOMORIS recommendation, derived from the terms in BSI Standard 200-4, ch. 7 and 8): in the test, T0 stands for the declaration of the emergency, i.e. the start of recovery; detection and alerting (BAO response time) are not included. The achieved recovery time (RTA) runs from T0 to handover T1 to the business unit. For data loss, T0 also counts as the assumed time of the outage: the RPA is the interval between the timestamp of the most recent fully restored data state and T0.
| Metric | Target | Actual | Met |
|---|---|---|---|
| Recovery time: RTA = T1 minus T0 | RTO ____ h | ____ h ____ min | yes / no |
| Data loss: RPA = T0 minus timestamp of the data state | RPO ____ h | ____ h | yes / no |
| Backup cycle according to the backup plan | no more than RPO | ____ h | yes / no |
| RTA plus BAO response time | below MTPD ____ h | ____ h | yes / no |
- Before restoring, checked whether the backup might already contain malware; worked with a copy of the backup or with write protection (BSI ransomware catalog of measures, ch. 2).
- Data fully restored and at the state of the last available backup (NIST SP 800-34, 4.4); verification method, e.g. count, size, checksums: __________
- Configuration data and data stored in cloud services restored (Implementing Regulation Annex point 4.2.2(b)); encrypted backup decrypted with the key from separate storage (CON.3.A13, elevated protection needs).
- All functions checked, ready for normal operations (NIST SP 800-34, 4.4); confirmed by [Name, role] from the business unit.
- Offline copy: access attempt with (domain) administrator rights failed (ransomware catalog of measures, ch. 2). Immutable copy: deletion or overwriting of a test backup rejected (overwriting: CON.3.A14; deletion: TOMORIS recommendation).
- The instructions were understandable, complete and technically correct; deviations are recorded in Part D (BSI Standard 200-4, ch. 13.9).
Part D: Result, findings and sign-off
Per tested resource: successful, partially successful or not successful (BSI Standard 200-4, ch. 13.9.2, Table 40). Overall result: passed / failed, because under ISO 22398 a test is an exercise with an objectively measured result (ch. 13). An error-free exercise is not a success criterion; an exercise is also successful if a need for correction is identified and used for improvement (ch. 13.10).
| Resource, test activity | Result | Finding, cause | Corrective action | Owner, deadline |
|---|---|---|---|---|
| __________ | __________ | __________ | __________ | [Name, role], [MM/DD/YYYY] |
| __________ | __________ | __________ | __________ | [Name, role], [MM/DD/YYYY] |
| __________ | __________ | __________ | __________ | [Name, role], [MM/DD/YYYY] |
| __________ | __________ | __________ | __________ | [Name, role], [MM/DD/YYYY] |
NIS2 entities document test results and take corrective action where necessary (Implementing Regulation Annex point 4.2.6); lessons learned from tests are incorporated into the plans (point 4.1.4). The BSI recommends identifying causes, monitoring improvements and reporting delays to management (DER.4.A14, elevated protection needs). TOMORIS recommendation: close a finding only after a successful retest. If the Annex applies to you via § 2 NISV 2026 and you cannot meet point 4.2.6 temporarily or because of your size, § 4 NISV 2026 requires compensating measures, documented with reasons and reviewed for effectiveness at least annually.
| Role | Name, role | Date | Signature |
|---|---|---|---|
| Exercise lead: performed and logged | [Name, role] | [MM/DD/YYYY] | __________ |
| IT owner or IT service provider | [Name, role] | [MM/DD/YYYY] | __________ |
| Business unit: functionality confirmed | [Name, role] | [MM/DD/YYYY] | __________ |
| Management: result and measures approved | [Name, role] | [MM/DD/YYYY] | __________ |
Common mistakes
- The status “Backup successful” does not replace a restore test (CON.3, threat 2.2).
- Instructions and keys are not stored separately and fail along with everything else (threats 2.4 and 2.8).
- The configuration is missing from the backup; only content data is backed up (Implementing Regulation Annex point 4.2.2(b)).
- Always using the same exercise scenario increases the risk of operational blindness (BSI Standard 200-4, ch. 13.2).
Sources
- BSI IT-Grundschutz-Kompendium, module CON.3 Backup Concept, Edition 2023 — Threats 2.2, 2.4, 2.8; A4, A6, A9, A13, A14, A15
https://www.bsi.bund.de/SharedDocs/Downloads/DE/BSI/Grundschutz/IT-GS-Kompendium_Einzel_PDFs_2023/03_CON_Konzepte_und_Vorgehensweisen/CON_3_Datensicherungskonzept_Edition_2023.pdf?__blob=publicationFile&v=3 - BSI IT-Grundschutz-Kompendium, module DER.4 Business Continuity Management, Edition 2023 — Requirements DER.4.A1, A10, A14 and A16
https://www.bsi.bund.de/SharedDocs/Downloads/DE/BSI/Grundschutz/IT-GS-Kompendium_Einzel_PDFs_2023/05_DER_Detektion_und_Reaktion/DER_4_Notfallmanagement_Edition_2023.pdf?__blob=publicationFile&v=3 - BSI Standard 200-4 Business Continuity Management, version 1.0 (2023) — Ch. 2, 5.5.1, 7 to 8.2, 13 to 13.10; Tables 28, 29, 34, 36, 37, 40
https://www.bsi.bund.de/SharedDocs/Downloads/DE/BSI/Grundschutz/BSI_Standards/standard_200_4.pdf?__blob=publicationFile&v=8 - BSI: Grundschutz++, milestone plan — As of October 2026, accessed October 25, 2026
https://www.bsi.bund.de/DE/Themen/Unternehmen-und-Organisationen/Standards-und-Zertifizierung/Grundschutz-in-der-Informationssicherheit/Grundschutz-Plus-Plus/grundschutz-plus-plus_node.html - BSI: Grundschutz++ user catalog (GitHub) — NOT.4.16.1; as of October 22, 2026, pilot phase
https://github.com/BSI-Bund/Stand-der-Technik-Bibliothek - BSI: Ransomware catalog of measures, version 1.0 of February 23, 2022 — Ch. 2 Backups
https://www.bsi.bund.de/SharedDocs/Downloads/DE/BSI/Cyber-Sicherheit/Themen/Ransomware_Massnahmenkatalog.pdf?__blob=publicationFile - NIST SP 800-34 Rev. 1: Contingency Planning Guide for Federal Information Systems — Sections 3.1, 3.2.1, 3.5, 3.5.1, 3.5.4 and 4.4
https://nvlpubs.nist.gov/nistpubs/Legacy/SP/nistspecialpublication800-34r1.pdf - Implementing Regulation (EU) 2024/2690 — Art. 1; Annex points 4.1.4, 4.2.2, 4.2.3 and 4.2.6
https://eur-lex.europa.eu/eli/reg_impl/2024/2690/oj/deu - ENISA: Technical Implementation Guidance, version 1.0 (June 2025) — Points 4.1.4, 4.2.3 and 4.2.6, pp. 54, 57 and 59
https://www.enisa.europa.eu/sites/default/files/2025-06/ENISA_Technical_implementation_guidance_on_cybersecurity_risk_management_measures_version_1.0.pdf - NISV 2026, BGBl. II No. 290/2026 — § 2 and § 4, promulgated on October 1, 2026
https://www.ris.bka.gv.at/eli/bgbl/II/2026/290 - NISG 2026, BGBl. I No. 94/2025, RIS, version of October 25, 2026 — § 4 para. 2, § 27 para. 1, § 31 para. 1, § 32 para. 4 lit. c, § 51 para. 2
https://www.ris.bka.gv.at/GeltendeFassung.wxe?Abfrage=Bundesnormen&Gesetzesnummer=20013065 - Regulation (EU) 2016/679 (GDPR) — Art. 32(1)(c) and (d)
https://eur-lex.europa.eu/eli/reg/2016/679/oj/deu